Project Management · PMP

Project Management Professional (PMP) Certification Exam Practice Test

PMP practice questions cover project management decisions across planning, delivery, monitoring, and closure. The available scenarios include selecting predictive or adaptive approaches, handling scope requests, assessing risks, communicating with stakeholders, and applying earned value measures. They focus on choosing actions that support project objectives while accounting for constraints, uncertainty, and stakeholder needs.

Exam overview

Exam providerProject Management Institute
Exam codePMP
CategoryProject Management

About the Project Management Professional (PMP) Certification Exam

Project managers integrate scope, schedule, cost, quality, resources, communications, procurement, and risk rather than treating each as an isolated concern. Decisions may involve evaluating trade-offs, establishing change control, and explaining how proposed work contributes to organizational value. The practice bank also samples team decision-making, stakeholder engagement strategies, and communication choices for routine updates versus urgent issues. Other scenarios address recording threats, selecting a response such as avoidance, interpreting cost performance through earned value, and completing closure tasks such as resolving contracts and organizing records. These situations call for identifying the immediate problem, considering its effect on project objectives, and choosing a proportionate next action. Use them to connect project documents and techniques to the management decision each one supports.

Sample Practice Questions

Review a selection from this exam's published US Practice Tests practice bank.

Question 1

A project manager is facilitating a meeting where a decision must be made among several feasible options. The participants have relevant expertise, and their commitment to the decision will be important. Which decision-making approach is most appropriate?

  1. AMake the decision privately and announce it afterward
  2. BFacilitate a discussion that seeks a shared agreement among participants
  3. CPostpone the decision until every uncertainty is eliminated
  4. DSelect the option with the most detailed presentation
Show answerCorrect answer: B

When participants have relevant expertise and their commitment matters, facilitating a shared decision can improve both decision quality and ownership. Waiting for all uncertainty to disappear or choosing based on presentation detail is not a sound decision criterion.

Question 2

A project is nearing completion. The deliverables have been accepted, but several contracts remain open and project records have not been organized. What should the project manager do?

  1. ARelease the team immediately because acceptance is complete
  2. BComplete administrative and procurement closure activities and archive relevant records
  3. CBegin a new project using the same budget before closing this one
  4. DDelete working documents that are no longer in daily use
Show answerCorrect answer: B

Project closure includes completing applicable procurement and administrative activities, organizing and archiving records, and confirming that obligations are addressed. Acceptance alone does not complete all closure work.

Question 3

A team is deciding whether to use a predictive or adaptive delivery approach. Requirements are expected to change frequently, and stakeholders can provide feedback in short cycles. Which approach is most suitable?

  1. APredictive, because it minimizes stakeholder involvement
  2. BAdaptive, because frequent feedback can guide incremental delivery
  3. CPredictive, because changing requirements eliminate the need for planning
  4. DNeither; the project must wait until every requirement is fixed
Show answerCorrect answer: B

An adaptive approach is useful when requirements are uncertain or likely to evolve and stakeholders can provide regular feedback. Work can be delivered in increments and adjusted as learning occurs.

Question 4

A project manager is preparing a communication plan for a distributed team. Team members need routine status information, while an urgent issue may require immediate discussion. Which plan best addresses both needs?

  1. ASend all information in a monthly report, including urgent issues
  2. BUse a regular status update for routine information and a rapid channel such as a call for urgent issues
  3. CAsk each team member to choose an unrelated channel and schedule
  4. DCommunicate only when the sponsor requests an update
Show answerCorrect answer: B

A communication approach should match the information’s urgency and audience needs. Regular updates support predictable information flow, while a rapid channel enables timely response to urgent matters.

Question 5

A project manager wants to compare the actual cost of work performed with the budgeted cost of that same work. Which earned value measure provides this comparison?

  1. ACost variance
  2. BSchedule variance
  3. CEstimate at completion
  4. DPlanned value
Show answerCorrect answer: A

Cost variance is earned value minus actual cost, comparing the budgeted value of completed work with what was actually spent. Schedule variance compares earned value with planned value.

Question 6

A project has a fixed deadline and a fixed scope, and the sponsor asks the team to add a feature. What should the project manager do first?

  1. AAsk the team to work overtime so the feature can be added
  2. BAssess the proposed change’s impact and follow the agreed change control process
  3. CAdd the feature to the work plan because the sponsor requested it
  4. DRemove a different feature without consulting stakeholders
Show answerCorrect answer: B

A requested scope change should be evaluated for its effects on schedule, cost, resources, and other objectives, then handled through the project’s change control approach. This supports informed decisions rather than unauthorized changes.

Question 7

A project team is selecting a response to a threat. The team changes the project plan so that the threat can no longer affect the project objective. Which risk response strategy is this?

  1. AAvoid
  2. BTransfer
  3. CAccept
  4. DEscalate
Show answerCorrect answer: A

Avoidance changes the plan to eliminate the threat or protect the objective from its impact. Transfer shifts responsibility for managing an impact, while acceptance takes no proactive action beyond the chosen level of preparedness.

How to use this practice test

The free practice session presents up to 20 random questions from the 50-question bank. Answer each scenario before reviewing the results shown at the end. Use missed or uncertain answers to identify concepts to revisit, such as earned value comparisons, risk responses, change control, stakeholder engagement, and project closure.

Preparation tips

  • For earned value questions, distinguish actual cost (AC), earned value (EV), and planned value (PV) before selecting a cost or schedule measure.
  • When a requested feature affects fixed scope, schedule, or cost, identify the applicable change-control step before deciding whether to implement it.
  • For risk scenarios, separate an uncertain future event from an issue that has already occurred, then match the response strategy to the stated threat or opportunity.
  • Compare stakeholder influence, interest, and information needs when choosing engagement and communication approaches.
  • For closure scenarios, check acceptance, outstanding procurement or contract work, lessons learned, and records before considering the project complete.