Project Management · CAPM

Certified Associate in Project Management (CAPM) Certification Exam Practice Test

CAPM practice questions address foundational project management work, including defining scope, organizing deliverables, estimating effort and cost, and planning activity schedules. Scenarios also touch on risk assessment, stakeholder reporting, resource constraints, and evaluating proposed changes. These tasks call for clear distinctions between planning tools and processes, plus sound judgment about what information to gather before acting.

Exam overview

Exam providerProject Management Institute
Exam codeCAPM
CategoryProject Management

About the Certified Associate in Project Management (CAPM) Certification Exam

The question bank samples practical decisions across a project’s planning and control activities. You may identify a work breakdown structure as a way to decompose project work, choose a Gantt chart to display activity dates, or distinguish analogous estimating from other estimation approaches. Risk scenarios involve considering both probability and impact, while resource questions require attention to specialist availability and competing assignments. Other items ask how to respond to a requested scope change, assess its effects on project constraints, and communicate performance against agreed targets. These concepts support day-to-day tasks such as building a workable plan, surfacing uncertainty, coordinating people, and giving stakeholders useful status information. The scenarios emphasize selecting an appropriate next step or tool rather than memorizing terminology in isolation.

Sample Practice Questions

Review a selection from this exam's published US Practice Tests practice bank.

Question 1

A project team is assessing an uncertain event by considering how likely it is to occur and how much it could affect project objectives. What type of assessment is this?

  1. AQualitative risk analysis
  2. BQuantitative risk analysis
  3. CProduct acceptance testing
  4. DVariance analysis
Show answerCorrect answer: A

Qualitative risk analysis evaluates and prioritizes risks using characteristics such as probability and impact, often with relative ratings. Quantitative analysis uses numerical methods to estimate effects on objectives.

Question 2

A project manager needs to show the expected start and finish dates of activities across a calendar timeline. Which schedule presentation is most appropriate?

  1. AAffinity diagram
  2. BGantt chart
  3. CPareto chart
  4. DDecision tree
Show answerCorrect answer: B

A Gantt chart presents activities against a timeline, commonly showing planned start and finish dates and durations. The other options organize ideas, categorize frequency, or represent choices and possible outcomes.

Question 3

A stakeholder requests an additional feature after the project scope has been agreed. What is the most appropriate first step?

  1. AAsk the team to add it if they have spare capacity
  2. BEvaluate the request through the project's change control process
  3. CUpdate the schedule immediately and notify the sponsor afterward
  4. DReject the request because scope cannot change once approved
Show answerCorrect answer: B

A proposed change should be assessed through the agreed change control process so its effects on scope, schedule, cost, and other objectives can be considered before a decision is made.

Question 4

A project manager is preparing a cost estimate early in planning, when detailed information is limited, and uses costs from a similar completed project as a comparison. Which estimating technique is being used?

  1. AParametric estimating
  2. BAnalogous estimating
  3. CBottom-up estimating
  4. DThree-point estimating
Show answerCorrect answer: B

Analogous estimating uses information from a previous, similar project as the basis for estimating the current project. It is often used early when detailed information is not yet available.

Question 5

A project manager is preparing a report that compares the project’s current performance with agreed targets and communicates relevant information to stakeholders. What is this activity commonly called?

  1. APerformance reporting
  2. BResource leveling
  3. CProcurement closure
  4. DRequirements elicitation
Show answerCorrect answer: A

Performance reporting organizes and communicates project status and performance information against relevant expectations or targets. The other options concern schedule resources, contracts, and requirements gathering.

Question 6

A team is creating a hierarchical breakdown of the total project work into smaller, manageable components. What is this structure called?

  1. ARisk register
  2. BWork breakdown structure
  3. CStakeholder register
  4. DIssue log
Show answerCorrect answer: B

A work breakdown structure (WBS) decomposes the project scope and deliverables into progressively smaller components, helping organize and define the work to be performed.

Question 7

A project team needs to estimate the work required for a task by consulting people who have performed similar work before. What is this information-gathering approach called?

  1. AExpert judgment
  2. BTrend analysis
  3. CInspection
  4. DVariance analysis
Show answerCorrect answer: A

Expert judgment uses knowledge and experience from individuals or groups with relevant expertise to inform project decisions and estimates.

How to use this practice test

The free US Practice Tests bank contains 50 published questions. Each session presents up to 20 randomly selected questions, allowing you to work through a focused set of project-management scenarios. Results appear after the session; use them to identify concepts to revisit, such as estimating, scheduling, risk, or change evaluation.

Preparation tips

  • Practice decomposing sample project scope into deliverables and smaller work packages; distinguish the resulting work breakdown structure from a schedule.
  • For schedule questions, identify whether the task is to show activity timing, dependencies, or milestones before selecting a suitable presentation.
  • Compare analogous estimating with other estimation methods, and note what information is available when each estimate is prepared.
  • For risk scenarios, separate probability from impact and consider how each affects project objectives.
  • When a stakeholder requests a scope addition, consider how its effects on scope, schedule, cost, and other constraints should be evaluated before a decision.
Official sourceOfficial exam page ↗