CompTIA Project+ practice centers on the coordination and control of IT projects, from defining a business need to delivering work products and handing them over to operations. The available questions address project selection, requirements and acceptance, risk tracking, procurement choices, budget monitoring, and delivery approaches. They connect project-management terminology with decisions a project coordinator or manager may face during planning and execution.

Exam overview

Exam providerCompTIA
Exam codeNot listed
CategoryIT Certifications

About the CompTIA Project+ Certification Exam

Project work involves evaluating whether an investment supports organizational priorities, then translating the approved need into deliverables with measurable acceptance criteria. Teams distinguish verification—checking a product against written requirements—from validation of whether it addresses the intended business problem. They also select predictive or iterative delivery approaches, coordinate cycle reviews, and manage procurement by comparing internal capacity with external services and screening supplier proposals against mandatory requirements. Risk registers help track threats, assessments, and responses, while budget baselines provide a reference for comparing cumulative spending with the plan. Near completion, transition planning covers operational readiness, documentation, knowledge transfer, and responsibility for ongoing support. These concepts help professionals communicate status, identify decision points, and keep project outputs aligned with business needs.

Sample Practice Questions

Review a selection from this exam's published US Practice Tests practice bank.

Question 1

A project team is producing a deliverable that must satisfy measurable performance requirements. Which activity is primarily intended to determine whether the finished deliverable meets those requirements?

  1. AQuality control inspection or testing
  2. BStakeholder brainstorming
  3. CResource leveling
  4. DContract negotiation
Show answerCorrect answer: A

Quality control uses inspection, measurement, or testing to assess completed work against defined requirements and standards. This helps identify defects or nonconformance for appropriate action.

Question 2

A project team is using an iterative approach and has completed a short work cycle. Which meeting is intended for the team to reflect on its process and identify improvements for the next cycle?

  1. ARetrospective
  2. BKickoff meeting
  3. CProcurement review
  4. DFormal acceptance inspection
Show answerCorrect answer: A

A retrospective is a team reflection focused on how work was done and what process improvements could be made in a subsequent iteration. It differs from a review that primarily demonstrates or evaluates the product increment.

Question 3

A project manager is deciding whether to purchase a specialized service or use the organization's own staff. Which analysis directly supports this decision?

  1. AMake-or-buy analysis
  2. BVariance analysis
  3. CStakeholder salience analysis
  4. DRoot-cause analysis
Show answerCorrect answer: A

Make-or-buy analysis compares obtaining a service or product externally with producing or providing it internally, considering factors such as capability, cost, and availability.

Question 4

A project team is selecting a supplier. One proposal has the lowest price but does not meet a mandatory technical requirement. What should the team do?

  1. ASelect it because lowest price is the primary procurement goal
  2. BEvaluate proposals against the stated requirements and selection criteria
  3. CChange the technical requirement after selecting the supplier
  4. DAward the contract based on the supplier's presentation alone
Show answerCorrect answer: B

Supplier selection should follow documented requirements and evaluation criteria. A proposal that fails a mandatory requirement should not be chosen solely because it has the lowest price.

Question 5

A project manager wants to know whether the project’s intended outcomes are likely to justify its costs and support the organization’s priorities before substantial resources are committed. What should be reviewed?

  1. ABusiness case
  2. BMeeting minutes
  3. CDefect log
  4. DTeam directory
Show answerCorrect answer: A

A business case explains the rationale for an investment, including expected value, costs, and alignment with organizational needs. Meeting minutes, defect records, and directories do not make that investment justification.

Question 6

During a review, a deliverable meets its written requirements, but the customer says it does not solve the intended business problem. What should the team examine first?

  1. AWhether the project outcome still aligns with the stated business need
  2. BWhether the team used the latest version of its time-tracking tool
  3. CWhether every contributor attended the kickoff meeting
  4. DWhether the project has used its entire contingency reserve
Show answerCorrect answer: A

A deliverable can satisfy documented requirements yet fail to provide the intended value. Rechecking alignment with the business need helps determine whether goals, assumptions, or expectations have changed.

Question 7

A project team is identifying events that could negatively affect delivery. Which document records identified threats, their assessments, and planned responses?

  1. AIssue log
  2. BRisk register
  3. CDecision log
  4. DRequirements traceability matrix
Show answerCorrect answer: B

A risk register captures identified uncertainties, assessments such as probability and impact, and planned responses. An issue log tracks problems that have already occurred.

How to use this practice test

The free practice set draws up to 20 random questions from the 50-question bank for a session. Use each scenario to identify the project artifact, analysis, or decision that best fits the situation, then review the results to spot concepts that need closer attention.

Preparation tips

  • For each scenario, distinguish deliverable verification against measurable requirements from validation against the customer's intended business need.
  • Practice matching decisions to artifacts: use a risk register for threats and responses, and a budget baseline for planned-spending comparisons.
  • When evaluating procurement choices, compare internal capability with external sourcing and treat mandatory technical requirements as supplier-screening criteria.
  • Compare predictive and iterative delivery based on requirement stability and work sequence; associate retrospectives with process improvement between cycles.
  • For project closeout, outline an operations handoff that includes documentation, knowledge transfer, readiness, and support ownership.